Please select the month you wish to view the house build timeline of.
April
May
June
July
April Timeline
| 15th Ground breaking at building site | 23rd Foundation work continues |
| 16th Stake house on lot | 24th Finish foundation work and Home Builders City wide bus tour |
| 17th Begin excavation of basement | 25th Back fill basement and install electric panel for electric service |
| 18th Finish excavation and install water and sewer | 28th Install underground plumbing |
| 21st Foundation work begins | 29th Pour basement floor and garage floor |
| 22nd Foundation work continues | 30th Finish basement floor and garage floor |
May Timeline
| 1st Framing begins, bearing walls and floor system | 16th Shingling continues and begin installing soffits and facia |
| 2nd Framing continues and finish floor and start main floor walls | 19th Finish shingling and finish soffits and facia |
| 5th Framing continues, main floor walls | 20th Sub-contractors begin , plumbing, electrical and HVAC, begin siding on exterior |
| 6th Framing continues and finish wall framing | 21st Subs continue work, siding work continues and brick work begins |
| 7th Frame garage walls and sheath exterior walls | 22nd Subs continue work, siding work continues and brick work continues |
| 8th Roof framing starts | 23rd Subs continues, siding work finishes and brick work finished |
| 9th Roof framing continues | 26th Subs continue work, start exterior decks |
| 12th Roof framing continues | 27th Subs finish work and install prep work begins and inspections take place |
| 13th Roof framing continues | 28th Spray reflective paint, finish roofing, pour concrete front step, finish interior framing |
| 14th Finish roof framing | 29th Finish interior framing, install atic air shoots and plugs |
| 15th Install windows and exterior doors and also shingling starts | 30th Install exterior entrance doors, install garage door jambs |
June Timeline
| 2nd Sub-contractors begin work (Plumbers-HVAC-Electricians) | 17th Finish installing vapor barriers, seal around interior of windows, & doors |
| 3rd Subs continue work | 18th Begin to install siding on exterior |
| 4th Subs continue work | 19th Siding continues, Hers test |
| 5th Subs continue work | 20th Deliver drywall to house, finish siding |
| 6th Subs continue work | 23rd Begin hanging drywall |
| 9th Subs continue work, brick work begins | 24th Continue drywall |
| 10th Subs finish work, brick work continues | 25th Continue drywall |
| 11th Clean up and prep for insulation finish brick work | 26th Finish hanging drywall |
| 12th Insulating begins | 27th Begin taping drywall |
| 13th Finish insulation | 30th Continue taping drywall |
| 16th Install windows, begin to install poly vapor barriers |
July Timeline
| 1st Continue taping drywall | 17th Continue woodwork |
| 2nd Continue taping drywall | 18th Install cabinets, continue woodwork |
| 3rd Finish taping & texture of drywall | 21st Finish cabinets, continue woodwork, plumbers start finish work |
| 7th Begin interior painting | 22nd Continue woodwork, Begin exterior concrete flatwork |
| 8th Continue interior painting | 23rd Finish woodwork, concrete work continues |
| 9th Finish interior painting | 24th Begin cedar deck, finish concrete work, subs finish up work |
| 10th Paint exterior, Begin tiling, & hardwood floors | 25th Clean up & prep for carpet, work on deck finishes, Finish grade yard |
| 11th Continue tiling & hardwood floors | 28th Lay carpet, begin landscaping |
| 14th Finish tiling & hardwood floors, install garage doors & openers | 29th Finish odds & ends, paint exterior walk doors, continue landscaping |
| 15th Start interior woodwork, electricians start finish work | 30th Final clean up begins, duct cleaning, continue landscaping |
| 16th Continue woodwork | 31st Finish cleaning, finish landscaping |