House Build Timeline

Please select the month you wish to view the house build timeline of.

April

May

June

July

April Timeline
15th Ground breaking at building site 23rd Foundation work continues
16th Stake house on lot 24th Finish foundation work and Home Builders City wide bus tour 
17th Begin excavation of basement 25th Back fill basement and install electric panel for electric service
18th Finish excavation and install water and sewer 28th Install underground plumbing
21st Foundation work begins 29th Pour basement floor and garage floor
22nd Foundation work continues 30th Finish basement floor and garage floor

May Timeline
1st Framing begins, bearing walls and floor system 16th Shingling continues and begin installing soffits and facia
2nd Framing continues and finish floor and start main floor walls 19th Finish shingling and finish soffits and facia 
5th Framing continues, main floor walls 20th Sub-contractors begin , plumbing, electrical and HVAC, begin siding on exterior
6th Framing continues and finish wall framing 21st Subs continue work, siding work continues and brick work begins
7th Frame garage walls and sheath exterior walls 22nd Subs continue work, siding work continues and brick work continues
8th Roof framing starts 23rd Subs continues, siding work finishes and brick work finished
9th Roof framing continues 26th Subs continue work, start exterior decks
12th Roof framing continues 27th Subs finish work and install prep work begins and inspections take place
13th Roof framing continues 28th Spray reflective paint, finish roofing, pour concrete front step, finish interior framing
14th Finish roof framing 29th Finish interior framing, install atic air shoots and plugs
15th Install windows and exterior doors and also shingling starts 30th Install exterior entrance doors, install garage door jambs

June Timeline
2nd Sub-contractors begin work (Plumbers-HVAC-Electricians) 17th Finish installing vapor barriers, seal around interior of windows, & doors
3rd Subs continue work 18th Begin to install siding on exterior 
4th Subs continue work 19th Siding continues, Hers test
5th Subs continue work 20th Deliver drywall to house, finish siding
6th Subs continue work 23rd Begin hanging drywall
9th Subs continue work, brick work begins 24th Continue drywall
10th Subs finish work, brick work continues 25th Continue drywall
11th Clean up and prep for insulation finish brick work 26th Finish hanging drywall
12th Insulating begins 27th Begin taping drywall
13th Finish insulation 30th Continue taping drywall
16th Install windows, begin to install poly vapor barriers

July Timeline
1st Continue taping drywall 17th Continue woodwork 
2nd Continue taping drywall 18th Install cabinets, continue woodwork
3rd Finish taping & texture of drywall 21st Finish cabinets, continue woodwork, plumbers start finish work
7th Begin interior painting 22nd Continue woodwork, Begin exterior concrete flatwork
8th Continue interior painting 23rd Finish woodwork, concrete work continues
9th Finish interior painting 24th Begin cedar deck, finish concrete work, subs finish up work
10th Paint exterior, Begin tiling, & hardwood floors 25th Clean up & prep for carpet, work on deck finishes, Finish grade yard
11th Continue tiling & hardwood floors     28th Lay carpet, begin landscaping   
14th Finish tiling & hardwood floors, install garage doors & openers     29th Finish odds & ends, paint exterior walk doors, continue landscaping   
15th Start interior woodwork, electricians start finish work     30th Final clean up begins, duct cleaning, continue landscaping   
16th Continue woodwork     31st Finish cleaning, finish landscaping   

Home Page House Plans Energy Efficiency About Project House Build Timeline Builders And Contractors WebCam Video Upcoming Events E2 Project Photos